ExamAtlas
← العودة إلى الاختبارات التجريبية

اختبار تدريبي من ExamAtlas

اختبار PMP project management تجريبي 2026 و2027 - نموذج 1

تدرّب على قسم project management في اختبار PMP يتكوّن من 10 أسئلة، ويمتد لمدة 25 دقيقة، من خلال أسئلة تدريبية ونتيجة مباشرة تساعدك على مراجعة أدائك، لتحضير 2…

الوقت المتبقي

--:--

سيتم تنبيهك عند انتهاء الوقت.

القسم

project management

المستوى

Beginner

المدة

25 دقيقة

المهام

10

Managing Project Risks and Changes

A project manager is leading a software implementation project. The sponsor wants the project completed quickly, but several team members are concerned that the schedule is too aggressive. During a planning meeting, the project manager reviews the scope, identifies key risks, and asks the team to estimate the work more carefully.

One developer explains that a critical integration may take longer than expected because the external system has limited documentation. The project manager records this as a risk and discusses possible responses with the team. The team agrees to contact the external vendor early and create a backup plan.

As the project continues, the project manager holds regular meetings, tracks progress, and communicates updates to stakeholders. When a change request is submitted, the project manager does not approve it immediately. Instead, the impact on scope, schedule, cost, and quality is reviewed before a decision is made.

الأسئلة

اختر إجابة واحدة لكل سؤال، ثم اضغط Submit Test لعرض النتيجة مباشرة.

Q1. What should the project manager do when the team says the schedule is too aggressive?

Q2. When a change request is submitted, the project manager should first:

Q3. The limited documentation for the external system is best treated as:

Q4. Why does the project manager hold regular meetings?

Q5. The project manager’s overall approach is best described as:

Q6. A risk response plan is mainly used to:

Q7. Which areas should be reviewed for a change request?

Q8. The sponsor wants the project completed quickly. What should the project manager balance this with?

Q9. Which action shows good stakeholder communication?

Q10. What is a good early response to the integration risk?

قبل بدء الاختبار التجريبي

تعامل مع هذا الاختبار كتدريب منظم وليس كمحاولة عشوائية. جهّز وقتًا هادئًا، اقرأ التعليمات، ثم ابدأ الحل بدون فتح مصادر خارجية حتى تكون النتيجة أقرب لمستواك الحقيقي.

بعد الانتهاء، لا تكتفِ بالنتيجة. راجع الأسئلة التي أخطأت فيها، وحدد هل المشكلة في الفهم، الوقت، المفردات، أو طريقة قراءة السؤال. هذه الخطوة هي التي تحول الاختبار التجريبي إلى أداة تحسين فعلية.